We closed on November 12, 2026. This page keeps the house in one place: a model you can walk through as it stands today, and the same model with what we would like to build.
Walk through the house
All four floors, the yard, the driveway. Every outside door is open, so you can walk in and out.
Start at the foyer → After the buildWalk through the plan
The same house with the new garage, family room, rear addition, terrace and pool.
Start at the foyer → From outsideLook at it from any side
Turn the whole lot around and zoom. Switch between Today and After at the top of the screen.
Open the outside view →How to move: W A S D or the arrow keys to walk, drag to look around. On a phone, left thumb walks and the right thumb looks. The buttons on the right jump between floors; “Fly” shows the house from outside.
The plan now
The house as we bought it
- House
- Asphalt
- Pavers and stone
- Lot: 17,552 sq ft (0.40 acre), 120 ft along Bellevue Avenue.
- House: about 3,560 sq ft on three floors, plus a basement under the back half. The main part is 32.6 × 48.4 ft with the chimney end to the street.
- First floor: living room, office, dining room, breakfast room, kitchen, mudroom, powder room, and a two-car garage whose doors face the backyard.
- Second floor: primary bedroom with bath, closet and balcony, two more bedrooms, hall bath, laundry, and a den over the garage.
- Third floor: two bedrooms, a bath, a kitchenette and attic storage.
- Basement: unfinished, about 690 sq ft, with the boiler, water tank and air handler. The front half of the house sits on a crawl space.
- Yard: the driveway runs past the front door all the way to the back, so asphalt and pavers already cover close to the 30% the town allows.
The plan later
What we would like to build
- House today
- New
- Pool
- Terrace and paving
- New two-car garage beside the old one, 22 × 24 ft, with doors to the street. The driveway becomes a short straight run and stops at the garage.
- The old garage becomes the family room. Its floor comes up level with the kitchen and it opens to the backyard.
- One-story rear addition, 12 ft deep across the kitchen and family room, with glass doors along the back.
- Terrace level with the kitchen floor, steps down to a 14 × 30 ft pool.
- Guest suite in the roof over the new garage, entered from the den.
- Backyard gets its lawn back. Removing the long driveway and rear parking frees about 1,500 sq ft, which is what makes room for the terrace and pool within the 30% limit.
- Basement: finish the existing part, add a new basement under the rear addition. Not shown in the model yet.
- Staying as planned: porch roof as a balcony, new windows with the same 6-over-6 look, cedar shingles on everything new.
Numbers
Against the town’s limits
The lot is in the R-25 zone and in the historic district. Areas for today come from the survey; areas for the plan are from the concept model and will move once an architect measures.
| Rule | Allowed | Today | Plan | |
|---|---|---|---|---|
| Building footprint (14% of lot) | 2,457 sq ft | 1,941 · 11.1% | 2,898 · 16.5% | needs approval |
| Floor area (25% of lot; garage and basement not counted) | 4,388 sq ft | ≈ 3,560 · 20.3% | ≈ 4,680 · 26.6% | needs approval |
| Both side yards together (40% of lot width) | 48 ft | 63 ft | 41 ft | needs approval |
| Attached garage doors facing the street | not on wide lots | face the back | face the street | needs approval |
| Everything hard on the ground (30% of lot) | 5,266 sq ft | ≈ 5,180 · 29.5% | ≈ 5,190 · 29.6% | within limit |
| East side yard | 17 ft | 41 ft | 19 ft | within limit |
| Height | 35 ft | about 32 ft | unchanged | within limit |
Floor area in the plan: 3,560 today + 360 old garage turned into a room + 430 rear addition + about 330 guest suite. Without the guest suite the floor area is about 4,350 sq ft, which is inside the limit.
Timing
Realistic schedule
- Nov–Dec 2026Move in, agreed repairs, meet architects who know Summit.
- Jan–Mar 2027Measured drawings and first design. Informal talk with the zoning officer and the historic commission.
- Spring 2027Work that needs no special approval: windows, balcony, basement finish.
- Apr 2027File with the Zoning Board.
- Jun–Aug 2027Hearing, with room for one follow-up meeting.
- Sep–Oct 2027Construction drawings and building permit.
- Nov 2027–Sep 2028Construction, about ten months.